This page was exported from Top Exam Collection [ http://blog.topexamcollection.com ] Export date:Mon Jan 20 2:53:21 2025 / +0000 GMT ___________________________________________________ Title: [Q159-Q179] PRINCE2 PRINCE2-Foundation Practice Verified Answers - Pass Your Exams For Sure! [2022] --------------------------------------------------- PRINCE2 PRINCE2-Foundation Practice Verified Answers - Pass Your Exams For Sure! [2022] Valid Way To Pass PRINCE2 Certification's PRINCE2-Foundation Exam NEW QUESTION 159Which is NOT a purpose of the Initiating a Project process?  Enable a Project Board decision about the commitment of resources to a project  Enable an organization to understand the work that needs to be done to deliver a project’s products before a project is approved  Establish solid foundations for a project  Enable the Project Board to decide whether it is worthwhile to initiate a project NEW QUESTION 160How many roles make up the Project Board?  One  Two  Three  Four NEW QUESTION 161How does the use of product descriptions support the ‘focus on products’ principle?  By documenting the scope tolerance for the project  By documenting the quality expected by the customer  By documenting the costs for the product  By documenting the delivery date for the product ExplanationReference http://prince2.wiki/Focus_on_productsNEW QUESTION 162Which is a purpose of the ‘identify the risks’ step within the recommended risk management procedure?  To identify responses to risks documented in the business case  To identify information about the project environment and objectives  To identify the roles to be involved in risk management activities  To identify uncertainties that may impact on the delivery of the project objectives Explanation/Reference:Reference http://prince2.wiki/Risk#The_Risk_Management_ProcedureNEW QUESTION 163Which is a recommended quality review team role?  Project Manager  Assurance  Project Support  Administrator Section: Volume BExplanation/Reference:NEW QUESTION 164Which is a purpose of the quality theme?  To check that the project is viable and achievable  To ensure that the project outputs are agreed  To ensure that formal issues are recorded  To enable the project to be managed according to plan Section: Volume BNEW QUESTION 165Why is it crucial that the Project Product Description clearly defines acceptance methods?  Enables Project Assurance to authorize quality activities  Defines how all project products will be reviewed and approved  Defines how it will be proven that the completed project product meets the customer’s expectations  Provides confirmation that all project products have met their quality criteria Section: Volume BNEW QUESTION 166Which is a purpose of the Quality theme?  Establish how the project will ensure that all products created meet their requirements  Establish quality assurance to maintain the quality management system  Identify all the products of the project to ensure the scope has been adequately defined  Determine the communication needs of the organization’s quality assurance function NEW QUESTION 167How does the use of product descriptions support the ‘focus on products’ principle?  By documenting the scope tolerance for the project  By documenting the quality expected by the customer  By documenting the costs for the product  By documenting the delivery date for the product Explanation/Reference:Reference http://prince2.wiki/Focus_on_productsNEW QUESTION 168Which is a purpose of the quality theme?  To establish how the project will ensure that all products created meet their requirements  To establish baselines against which any changes to products can be assessed  To identify all the products of the project to ensure the scope has been adequately defined  To determine the communication needs of the organization’s quality assurance function Section: Volume BNEW QUESTION 169Which is a purpose of the Initiating a Project process?  Decide if it is worthwhile to initiate a project  Decide on the project approach  Establish solid foundations for a project  Identify the number of Work Packages required NEW QUESTION 170Which is a benefit of using PRINCE2?  Is a method specifically designed for technical projects  Provides for the efficient and economic use of management time  Includes many of the proven planning techniques, such as critical path analysis  Can be used to manage both projects and programmes Section: Volume ANEW QUESTION 171Which should be provided by a project mandate?  Terms of reference  Detailed Business Case  Stage tolerances  Initiation Stage Plan NEW QUESTION 172Which is NOT one of the PRINCE2 integrated elements?  Tailoring PRINCE2 to the project environment  The processes  The products  The themes NEW QUESTION 173Which is a purpose of the Starting up a Project process?  Prevent poorly conceived projects from ever being initiated  Ensure the communication requirements of all stakeholders are documented  Learn lessons from this project  Document how changes required by corporate or programme management will be reviewed NEW QUESTION 174Why is the ‘learn from experience’ principle applied to a project?  To enable the project team to repeat successes from previous projects  To enable the project team to develop a business case for the project  To allow the project to be divided into management stages  To enable the project team to use tolerances to delegate authority Section: Volume BExplanation/Reference: https://link.springer.com/chapter/10.1007/978-3-319-23000-9_4NEW QUESTION 175Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?  Manage by stages  Manage by exception  Continued business justification  Learn from experience NEW QUESTION 176Which is a purpose of the Risk theme?  Establish a method for the implementation of continuous improvement during the project  Identify, assess and control problemsthat have occurred  Provide the Project Board with a time-driven control to capture all project risks  Establish a cost-effective procedure to identify, assess and control risks NEW QUESTION 177Which is an objective of the ‘directing a project’ process?  To tailor the project’s products and roles so that the project suits the circumstances  To respond to the project mandate by starting up a project  To provide an interface between the project and corporate management  To ensure the stage products are delivered to the stated quality standards Reference:https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project-process-in-princNEW QUESTION 178Which is part of quality control?  Document the project’s acceptance criteria in the Project Product Description  Define the quality responsibilities of those involved in the production of the products  Produce quality records to show that the planned quality activities have been carried out  Maintain the corporate organization’s quality management system NEW QUESTION 179Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?  Continued business justification  Defined roles and responsibilities  Manage by exception  Manage by stages Section: Volume BExplanation/Reference: http://prince2.wiki/Manage_by_exception Loading … PRINCE2 PRINCE2-Foundation Pre-Exam Practice Tests | TopExamCollection: https://www.topexamcollection.com/PRINCE2-Foundation-vce-collection.html --------------------------------------------------- Images: https://blog.topexamcollection.com/wp-content/plugins/watu/loading.gif https://blog.topexamcollection.com/wp-content/plugins/watu/loading.gif --------------------------------------------------- --------------------------------------------------- Post date: 2022-04-16 16:12:37 Post date GMT: 2022-04-16 16:12:37 Post modified date: 2022-04-16 16:12:37 Post modified date GMT: 2022-04-16 16:12:37