PRINCE2-Practitioner Updated Exam Dumps [2022] Practice Valid Exam Dumps Question [Q170-Q188]

July 11, 2022 0 Comments

Rate this post

PRINCE2-Practitioner Updated Exam Dumps [2022] Practice Valid Exam Dumps Question

PRINCE2-Practitioner Sample with Accurate & Updated Questions

How to book the PRINCE2-Practitioner Certified Exam

To take the PRINCE2 Practitioner examination you must provide proof of having passed one of the following:

  • Project Professional Qualification (PPQ)
  • IPMA Level B® (Certified Senior Project Manager)
  • Certified Associate in Project Management (CAPM)
  • IPMA Level A® (Certified Projects Director)
  • For more information on which certifications are now recognized as approved prior learning for the PRINCE2 Practitioner certification, please visit Official Website
  • IPMA Level C® (Certified Project Manager)
  • PRINCE2 Foundation (or higher) – this only applies to certificates obtained after 1 January 2009
  • IPMA Level D® (Certified Project Management Associate)

PRINCE2-Practitioner Certified Professional salary

The average salary of a PRINCE2-Practitioner Certified exam certified expert in:

  • United State – 60,000 USD
  • England – 35,500 POUND
  • India – 6,50,000 INR
  • Europe – 45,000 EURO

PRINCE2-Practitioner Exam Certification Path

You may be having some questions regarding how you can buy our PRINCE2 exam dumps, we are providing a flexible option of making payment using PayPal where you can make payment using a credit card. If you are purchasing from a country like India, then you can visit their website for more information about that payment details. Being a customer, if you are having any queries or looking for bulk purchase or additional discount, then feel free to drop us an email at [info@TopExamCollection](mailto:info@TopExamCollection).

What about once you are done with the purchase, do not worry, our services never use to get stop only after selling one product to you, we provide after-sales services as well like you will always get updated PRINCE2-Practitioner exam dumps in your profile because we use review PRINCE2-Practitioner exam dumps and get them updated regularly. you are getting multiple options to access our provided exam dumps first one is accessing it through an online exam simulator where you can practice all the questions and answer, which provide a lot of insights like about how you are performing, how much you had scored in your given attempt, what is the correct answer with a clear explanation of every question, you can find all these benefits from our provided online exam simulator. The second option to access our purchased exam dumps is using mobile applications, we already have a mobile application that you can download from the AppStore, play store, etc. and just log in with your username and password after that you are good and start using our mobile-friendly app. Anytime, if you feel that you need to have some support from our team, you can reach out to us by simply dropping an email, we will connect to you back on priority because we believe in providing customer service and satisfaction.

 

NO.170 Which 2 statements should be recorded under the Costs heading?

 
 
 
 
 

NO.171 Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH’s documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.
Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of the Outsourcing project, the proposed option exceeds tolerance. Nhat is the next action the Project Manager should consider?

 
 
 
 

NO.172 Which principle is central to the quality theme and provides explicit understanding of what the project will create?

 
 
 
 

NO.173 Which statement best explains the purpose of Tailor to suit the project environment?

 
 
 
 

NO.174 Which 2 statements apply to the Customer’s quality expectations section?

 
 
 
 
 

NO.175 Scenario
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company’s image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar.
It has yet be decided which of the photographers to use.
Which 2 statements explain why the Sales Manager should be appointed as User Assurance for this project?

 
 
 
 
 

NO.176 The project is in stage 2. The project manager is reviewing stage status and has collected the checkpoint
reports from the team managers. These show that the products are being completed on schedule. However,
project support has raised issues that quality reviews have not been completed as agreed. The project
manager reports in the highlight report that the stage is progressing well.
Is this appropriate, and why?

 
 
 
 

NO.177 There are four steps in the Risk Management procedure, what are they?

 
 
 
 

NO.178 This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Introduction section?

 
 
 

NO.179 After preparing the stage 3 plan, the project manager left the company. The project board has decided that, as the stage plan has been agreed, it will not appoint a project manager for stage 3. The team managers will report directly to the project board and will prepare highlight reports instead of checkpoint reports.
Is this an appropriate tailoring of the roles in the ‘managing a stage boundary’ process?

 
 
 
 

NO.180 Which principle is central to the quality theme and provides explicit understanding of what the project will create?

 
 
 
 

NO.181 Which 2 statements should be recorded under the Expected dis-benefits heading?

 
 
 
 
 

NO.182 Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PID). The PID includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality – results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Information needs for each interested party section?

 
 
 

NO.183 Which of the following is False?
A Successful project management team should.

 
 
 
 

NO.184 It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO’s customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
Which product should show that the project has been closed prematurely and has not achieved the objectives defined in the Project Initiation Documentation (PID)?

 
 
 
 

NO.185 Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
There is no mention of any Stage Plans, yet there are two further stages proposed. How will this be resolved?

 
 
 

NO.186 HOTSPOT
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month – correctly showing at public holidays and new company logo

Selected photographs- 12 professionally-produced photographs, showing different members of staff

Selected paper and selected envelope – for printing and mailing the calendar

Chosen label design – a competition to design a label will be held as part of this project

List of customers – names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing departments

Confirm compliance with the Data Protection Legislation

Create a design for each month – this will be done by the internal creative team

Select and appoint a professional photographer

Gather photograph design ideas from previous project and agree photographic session schedule

Prepare a production cost forecast

Select paper and envelope.

Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs

Hold the label design competition and choose the label design

Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +
£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement For each line identify the appropriate option, from options 1 to 6, that applies. Each option can be used once, more than once or not at all.
Hot Area:

NO.187 Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Monitoring and control section?

 
 
 
 
 

NO.188 The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor’s calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under the Roles and responsibilities heading?

 
 
 
 
 

Pass PRINCE2 PRINCE2-Practitioner Premium Files Test Engine pdf – Free Dumps Collection: https://www.topexamcollection.com/PRINCE2-Practitioner-vce-collection.html

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below