[Jul 15, 2023] L4M3 Exam Dumps – CIPS Practice Test Questions [Q85-Q106]

Juli 15, 2023 0 Kommentare

Diesen Beitrag bewerten

[Jul 15, 2023] L4M3 Exam Dumps – CIPS Practice Test Questions

New Real L4M3 Exam Dumps Questions

FRAGE 85
A procurement professional is drafting payment terms for a commercial contract. He is considering about payment method if defective products are found. Which of the following should be embedded in payment terms to control this issue?

 
 
 
 

FRAGE 86
Which of the following is the international standard for labelling hazardous substances?

 
 
 
 

FRAGE 87
Which of the following can be considered as implied terms in a contract?
1. Case law
2. Statute
3. Trade custom
4. A term can never be implied, it must always be expressed by the parties

 
 
 
 

FRAGE 88
In common law, which of the following documents is legally binding without the need for consideration?

 
 
 
 

FRAGE 89
Which of the following are implied terms in sales contracts? Select THREE that apply.

 
 
 
 
 
 

FRAGE 90
CMS Corp goes into a gainshare agreement with the contractor, EIP Ltd. Both parties agree that the final fee will be calculated on target cost – target fee basis. Which of the following will affect the final fee payable in this gainshare agreement? Select TWO that apply:

 
 
 
 
 

FRAGE 91
Welcher der folgenden Bereiche regelt die Schranken für die Erbringung von Dienstleistungen zwischen Ländern?

 
 
 
 

FRAGE 92
A purchase order can become a contract between supplier and purchaser if it is…?

 
 
 
 

FRAGE 93
Standard terms and conditions should become the governing terms for which group of items?

 
 
 
 

FRAGE 94
Which of the following documents are likely to have legal standing? Select TWO that apply:

 
 
 
 
 

FRAGE 95
In which of the following section of a specification, requirements for training to use the equipment will be set out?

 
 
 
 

FRAGE 96
Which of the following is most likely to be an one-off contract?

 
 
 
 

FRAGE 97
Which of the following is always automatically considered as a contract?

 
 
 
 

FRAGE 98
Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.
Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.
Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.
Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?

 
 
 
 

FRAGE 99
Which of the following are likely to be express terms in a contract?
1. Legislation
2. Custom and practice
3. Contract particulars
4. Terms and conditions

 
 
 
 

FRAGE 100
A retailer prefers to display its best selling products and promotion programme on the building windows. According to rule of contract formation, this act will generally constitute…?

 
 
 
 

FRAGE 101
Welche der folgenden Aussagen zum RFQ-Prozess sind richtig? Wählen Sie ZWEI aus, die zutreffen.

 
 
 
 
 

FRAGE 102
Which of the following statement is true about one-off contract?

 
 
 
 

FRAGE 103
Consequences and actions that arise from certain KPI scores must be…? Select TWO that apply.

 
 
 
 
 

FRAGE 104
Which of the following encourages social and environmental criteria in public sector contracting in the UK?

 
 
 
 

FRAGE 105
GPP, der Arbeitgeber, und Prosolia UK, der Auftragnehmer, schlossen fünf EPC-Verträge für die Entwicklung von fünf verschiedenen Solarkraftwerken im Vereinigten Königreich. Vier der fünf Anlagen wurden nicht zu den vorgesehenen Terminen in Betrieb genommen, wobei die Verzögerungen zwischen 44 und 285 Tagen lagen.
Neben anderen Ansprüchen forderte GPP, handelnd durch seine beiden Investmentgesellschaften, in allen vier Verträgen einen pauschalen Schadenersatz von 500 £ pro Tag, weil Prosolia UK die Anlagen nicht fristgerecht fertiggestellt hatte. Der geforderte pauschale Schadenersatz belief sich auf insgesamt 1.804.221 £ für die vier verspäteten Verträge.
Prosolia erhob neben verschiedenen anderen Einwendungen die Einrede, dass die in jedem Vertrag enthaltene Bestimmung über den pauschalierten Schadensersatz eine Vertragsstrafe darstelle und daher nicht gegen sie durchsetzbar sei. Ist Prosolia vertraglich verpflichtet, die Zahlung an den Kläger zu leisten?

 
 
 
 

FRAGE 106
Welche der folgenden Bedingungen müssen erfüllt sein, damit der Widerruf des Angebots gültig ist?
1. Der Angebotsempfänger hat das Angebot noch nicht erhalten
2. Der Widerruf des Angebots muss dem Angebotsempfänger mitgeteilt werden
3. Der Widerruf des Angebots muss per E-Mail erfolgen
4. Der Angebotsempfänger hat das Angebot noch nicht angenommen

 
 
 
 

Pass Your L4M3 Exam Easily with Accurate PDF Questions: https://www.topexamcollection.com/L4M3-vce-collection.html

         

Schreibe einen Kommentar

Deine E-Mail-Adresse wird nicht veröffentlicht. Erforderliche Felder sind mit * markiert

Geben Sie den Text aus dem Bild unten ein