100%試験の合格保証[Q16-Q40]でCAPMの質問回答の無料アップデートを準備する




Prepare CAPM Question Answers Free Update With 100% Exam Passing Guarantee [2024]

Dumps Real PMI CAPM Exam Questions [Updated 2024]


What is the duration of CAPM Exam

The duration of this exam is 3 hours.

 

質問16
Which is the appropriate tool to identify the possible correlation two elements in aprocess?

 
 
 
 

質問17
Which of the following set of elements is part of an effective communications management plan?

 
 
 
 

質問18
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

 
 
 
 

質問19
Which component of the project charter defines what the project’s success will look like?

 
 
 
 

質問20
The process of defining how the project scope will be validated and controlled is known as:

 
 
 
 

質問21
Which are the main objectives of Project Risk Management?

 
 
 
 

質問22
Budgets reserved for unplanned changes to project scope and cost are:

 
 
 
 

質問23
The project scope statement and resource calendars are inputs to which Project Time Management process?

 
 
 
 

質問24
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

 
 
 
 

質問25
What risk technique is used to quantify the probability and impact of risks on project objectives?

 
 
 
 

質問26
Directing another person to get from one to another using a known set of expected behaviors are the ability to lead a team and inspire them to do their jobs well is related to?

 
 
 
 

質問27
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

 
 
 
 

質問28
Which are examples of processes that may be used once or at predefined points in the project life cycle?

 
 
 
 

質問29
A project using the agile/adaptive approach has reached the Project Integration Management phase.

is the project manager’s key responsibility during this phase?

 
 
 
 

質問30
組織のプロセス資産
ツール&テクニック
1.専門家の判断
2. Meetings
出力
1. Scope management plan
2. Requirements management plan
4.Which tool or technique is an examination of industry and specific vendor capabilities?

 
 
 
 

質問31
Which of the following factors within a company cloud trigger the creation of a project?

 
 
 
 

質問32
Which of the following tools and techniques is used in the Develop Project Team process?

 
 
 
 

質問33
A project manager is performing a specific process and has……….is being referred to?
A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?

 
 
 
 

質問34
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

 
 
 
 

質問35
Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

 
 
 
 

質問36
Which provides the basic framework for managing a project?

 
 
 
 

質問37
Lessons learned are created and project resources are released in which Process Group?

 
 
 
 

質問38
An output of the Manage Project Team process is:

 
 
 
 

質問39
Whose approval may be required for change requests after change control board (CCB) approval?

 
 
 
 

質問40
Activity cost estimates are quantitative assessments of the probable costs required to:

 
 
 
 

CAPM Exam Dumps, CAPM Practice Test Questions: https://www.topexamcollection.com/CAPM-vce-collection.html 1

リンク
  1. https://www.topexamcollection.com/CAPM-vce-collect ion.html
Post date: 2024-05-31 12:33:34
Post date GMT: 2024-05-31 12:33:34

Post modified date: 2024-05-31 12:33:34
Post modified date GMT: 2024-05-31 12:33:34

Export date: Sat Jan 18 10:18:13 2025 / +0000 GMT
このページはTop Exam Collectionからエクスポートしたものです。 [ http://blog.topexamcollection.com ]